ree before a decision is reachedРA. all members become committedРB. decisions are reached slowlyРC. integrity is developedРD. future decision making ability is enhancedРE. All of the aboveРР正确答案:EР项目管理师考试题目下载5卷 第3卷Р Р153 There are hard causes of conflict (e.g. conflicting schedules) and soft causes. Soft causes are as important as hard causes. Soft causes include diversity of disciplinary expertise, _____, and the project manager's power of reward and punishment.РA. Performance tradeoffsРB. Ambiguity of rolesРC. Administrative proceduresРРРD. Determining earned valueРР正确答案:BР Р编制项目进度表是一个不断反复的过程,如果开始和结束的日期都不现实的话,项目很可能无法按照计划完成。既然你认识到了进度控制的重要性,你和你的团队正致力于明确如何管理进度变更。你将最终的结果写在哪一个文件里?РA、 进度变更控制程序РB、 进度管理计划РC、 进度风险计划РD、 服务水平协议РР正确答案:BР Р项目章程是由建立的 ( )РA.上层管理机构РB.客户РC.项目经理РD.A及C.РР正确答案:D