has prepared a CPM schedule for your review. You notice that one node has six inputs (including two dummy activities) and four outputs (which include one dummy activity). Select the correct statement from the following:РРРA. This is a valid representation if the logic is correct.РB. This is invalid because a node can have a maximum of one dummy input representation if the logic is correct.РC. This is invalid because nodes cannot have both dummy inputs and dummy outputs.РD. This is a invalid because the number of outputs must equal the number of inputs.РE. This is invalid because a maximum of two inputs and two outputs are allowed using the critical path methodРР正确答案:AР Р执行任务的个体员工РA、 对结果符合要求或规范承担最终责任РB、 是重大项目组设计的一部分,只有项目经理了解项目组的性质РC、 不能对整体项目起到明显作用,РD、 不应该关心任务质量,因为对于整体项目范围而言,他/她的贡献是微不足道的