an early start time of _____ weeks and an early finish time of _____ weeks.РA. 11, 13РB. 12, 14РC. 13, 15РD. 14, 16РE. 15, 17РР正确答案:EР Р合同收尾与项目管理收尾之间的关键差别为何 ( )РA.合同完工是项目完工正式生效РB.合同完工包括修订最终结果的记录РC.合同完工包括产品核证РD.项目管理收尾包括采购审计РР正确答案:CРРР РWhich of the following would most likely not be an essential objective of a project team kick-off meetingРA . Create a project technology master planРB . Get team members to know one anotherРC . Identify project problem areasРD . Obtain individual and group commitmentsРE . Identify the project coordinatorРР正确答案:AР Р8 Fixed-price contracts place more risk on the _____ .РA. ownerРB contractorРC. sellerРD. B and CРE. All of the aboveРР正确答案:DР Р160 The process of choosing/documenting the best approach to achieve the project objectives is part of: