ssage to several subordinates. What is the best medium by which the manager can get his message across?РA. OralРB. WrittenРC. NonverbalРD. A and B onlyРE. A, B, and CРР正确答案:EР Р● Including the customer in the process of project planning is:РA Slow and counterproductive.РB Essential in the definition and documentation of project goals.РC Necessary, but of limited value.РРРD Unnecessary because project goals are defined in the proposal stage.РE None of the above.РР正确答案:BР РA legally binding document offered unilaterally is a _____ .РA purchase orderРB scope of work descriptionРC contract stipulationРD level of effort proposalРE request for proposalРР正确答案:AР项目管理师试题7篇 第3篇Р Р买方已经与卖方达成了一个成本加酬金合同。合同设定的成本为30万美元,目标费为4万美元,分配比例为80/20,最高费为6万美元,最低为1万美元。如果卖方实际成本为38万美元,则买方实际支付的酬金为:РA、$104,000