on.)РE All of the above.РР正确答案:EР Р102 Using the situation stated in the Special window, which WBS element has a favorable cost variance of $150?РA. Element PРB. Element QРC. Element RРD. Element SРРРE. None of the aboveРР正确答案:CР Р一个订单是哪一种合同形式的例子?( )РA.单方面的РB.双方面的РC.三方面的РD.可分的РР正确答案:AР Р项目经理常使用什么工具以识别与项目有关的各种费用( )РA.材料清单РB.甘特图РC.箭线网络图РD.工作分解结构РР正确答案:DР项目管理师经典例题8章 第4章Р РРР166 The _____ specification delineates specific measurable capabilities or parameters for which a product can be tested as part of the acceptance procedure.РA. PerformanceРB. FunctionalРC. TechnicalРD. Base LineРE. None of the aboveРР正确答案:AР Р121 Using the WBS in the Special window, an instance of a work package is:РA. Build houseРB. ExcavateРC. Prepare FoundationРD. B and CРE. None of the aboveРР正确答案:E