段内挖方Р平均运距Р外借土方Р平均运距Р1标Р6709074.23Р7379981.65Р4390415.00Р1.0Km内Р2989566.65Р1.6Km内Р2标Р6475315.93Р7122847.52Р1771891.00Р1.2Km内Р2316491.35Р1.7Km内Р3034465.17Р2.4Km内Р3标Р6301885.78Р6932074.36Р2979892.00Р1.3Km内Р3952182.36Р2.4Km内Р4标Р5874264.53Р6461690.98Р3175008.00Р1.0Km内Р3286682.98Р1.6Km内Р5标Р5498129.00Р6047941.90Р5881912.00Р1.0Km内Р166029.90Р1.2Km内Р合计Р30858669.47Р33944536.41Р18199118.00Р15745418.41Р三、工期要求Р工期按照业主的要求进行施工。Р四、土方平衡Р根据《项目修建性详细规划》中的测绘地形图测算,本项目规划区内填挖工程量如下:Р序号Р区域Р填方(m3)Р填方*1.1Р挖方(m3)Р外借(+)Р外运(-)Р1Р一期Р30858669.20Р33944536.41Р18199118.00Р+15745418.41Р2Р二期Р28406691.00Р31247360.10Р65510236.00Р-34262875.90Р3Р三期Р62099227.34Р68309150.07Р16255407.00Р+52053743.07Р合计Р121364587.54Р133501046.58Р99964761.00Р+33536285.58Р Р依据上表中数据,结合现场全场地考虑土方平衡问题,一期挖方18199118.00 m3,填方30858669.20 m3×1.1=33944536.41m3,填方欠缺