ake pads and stre ssed structural parts s hould be re-inspected. Note: In loading the boat for th is test, precautions should be taken to ensure that the stability of the boat is not adversely affected by free surface e ffects or the raising of the centre of gravity. 4 OVERHAUL OF ON-LOAD RELEASE GEAR Overhaul of on-load release gear includes: .1 dismantling of hook release units; .2 examination with regard to to lerances and design requirements; .3 adjustment of release gear system after assembly; .4 operational test as per abov e and with a load according to SOLAS regulation III/20.11.2.3; and .5 examination of vital parts with regard to defects and cracks. Note : Non-destructive examination (NDE) techni ques, such as dye rants (DPE), may be suitable. ***