全文预览

项目管理师每日一练5章

上传者:叶子黄了 |  格式:docx  |  页数:20 |  大小:18KB

文档介绍
DР РR D project managers in high-tech companies most often motivate using _____ power.РA ExpertРB RewardРC ReferentРD IdentificationРE None of the aboveРР正确答案:AР Р4 In general, groups will ____ the average individual problem solver on problems with multiple stages. A. Perform. better thanРРРB. Perform. worse thanРC. Take less time thanРD. Do about as well asРР正确答案:AР Р对一个风险事件的临时应对措施叫做:( )РA.工作项(work item)РB.工作包(work package)РC.权变措施(workaround)РD.工作分解结构(work breakdown structure)Р正确答案:C权变措施(workaround)是指为了应对那些事先没有识别出的或者是已经接受的风险而采取的临时应对措施。Р Р● The critical path in a network is the path that:РA Has the greatest degree of risk.РB Will elongate the project if the activities on this path take longer than anticipated.РC Must be completed before all other paths.РD All of the above.

收藏

分享

举报
下载此文档