x=0.6qL=0.6×18.18×0.45=4.91kNРτmax=QmaxS/(Ib)=4.91×103×125×10-6/(833×10-8×0.1)Р=0.74×106N/m2=0.74MPa<[τ]=1.4MPaР满足要求Р(3)、挠度验算(计算构件挠度时,各类荷载分项系数取1.0)Рq=1.0·q2· L=1.0×45.84×0.3=13.75kN/mРfmax=0.677qL4/(100EI)Р=0.677×13.75×103×0.454/(100×9×103×106×833×10-8)Р=0.00005m<[f]=L/400=0.45/400=0.0011mР满足要求Р四、横肋钢管验算Р横肋为两根φ48×3.5竖排捆在竖肋上,间距45cm,承受竖肋传递的荷载。横肋被加托撑的钢管顶住,跨径(即托撑间距)为60cm,按三等跨连续梁验算,验算荷载为集中荷载P=60.61×0.45×0.6=16.36kN,集中荷载处于每跨跨中。Р计算简图如下,计算公式参照《路桥施工计算手册》附表2-9(第764页)。РPРPРPР60cmР60cmР60cmР(1)、弯拉强度验算РMmax=0.175PL=0.175×16.36×0.6=1.72kN·mРσw =Mmax/W=1.72×103/(2×5.08×10-6) Р=169.3×106N/m2=169.3MPa<[σw]=205MPaР满足要求Р(2)、挠度验算(计算构件挠度时,各类荷载分项系数取1.0)РP=1.0· q2 ·L1· L2=1.0×45.84×0.45×0.6=12.38kN/mРfmax=1.146PL3/(100EI)Р=1.146×12.38×103×0.63/(100×2.1×105×106×12.19×10-8×2)Р=0.0006m<[f]=L/400=0.6/400=0.0015mР满足要求