– keep equipments, personnel, livestock etc. clear out of the site: Р 30S 30S 30S Р 5S 5S РSecond time: a long alarm following a short alarm, three times – blasting personnel evacuated and the access blocked; Р Р 20S 10S 20S 10S 20S 10SР 5S 5SРThird time: three short alarms - ignition; Р 10S 10S 10S Р 1S 1S РFourth time: a long alarm - eliminating the alarming, discharging the personnel, equipments, and livestock and so on. Р 60S Р5. During the blasting operation, all of the personnel and vehicles must be evacuated from the blasting alarming area. The instructions of the in-situ blasting administrator shall be strictly followed, or the consequence shall be borne by the violator himself or herself. Р6. All final explanation rights to this blasting notice belong to Sinohydro Corporation Ltd.